Keeping static durations when assigning resources

Ken Case kc at omnigroup.com
Fri Mar 30 14:05:40 PDT 2007


On Mar 30, 2007, at 11:30 AM, Doug Pinkerton wrote:
> While I understand the value of having OP calculate durations for  
> me when building complex projects, for the current job I simply  
> wish to assign resources and durations without them affecting one  
> another. I know that Task A will take 2 days if 3 of my resources  
> are assigned to it. I do not wish for that to be calculated for me.

You can tell OmniPlan whether assigning resources should preserve the  
duration or the effort by pulling up the Task:Information inspector  
and clicking on the appropriate icon to the right of the Effort or  
Duration field.

Hope this helps!

				Ken