Keeping static durations when assigning resources
Doug Pinkerton
pinkerton.doug at hardingacademymemphis.org
Fri Mar 30 11:30:33 PDT 2007
While I understand the value of having OP calculate durations for me
when building complex projects, for the current job I simply wish to
assign resources and durations without them affecting one another. I
know that Task A will take 2 days if 3 of my resources are assigned
to it. I do not wish for that to be calculated for me. I do not wish
to assign efficiency percentages to the resources. I do not wish for
the addition of a resource to affect the duration of the task. But I
DO wish for OP to manage the dependencies and to identify resource
conflicts. Is there a way temporarily to disable the effort/duration
recalculations? Bear with me if this is a stupid question. I'm new to
the software.
Thanks,
dp